🚧 Construction Alert: Tuesday, Oct. 20 & Wednesday, Oct. 21 🚧Â
What to expect:
Tuesday, Oct. 20 | 4 a.m. to 3 p.m.
🔸 Crews will pour concrete for the approach slabs on the eastern bridge span beginning at the north end.
🔸 Please watch for trucks entering and exiting the job site and expect additional lighting and noise related to construction in the project area.
Wednesday, Oct. 21 | 7 a.m. to 3 p.m.
🔸 Motorists should anticipate intermittent traffic delays starting at 7 a.m. Motorists may use Belardo Road as an alternate route.
🔸 Concrete trucks will temporarily occupy the northbound lane of S. Palm Canyon Drive
🔸 Flaggers will alternate northbound and southbound traffic through the area.
🔹 Please follow flagger instructions, reduce speed and allow extra travel time through the project area.
✨ Businesses remain open and accessible during construction. ✨
This information may change due to weather or field conditions.
Stay updated:
760-502-0072 | SouthPalmCanyonBridge.com