Posts by Samira Obeid
🚧 Construction Alert: Thursday and Friday, Oct. 1 and 2 🚧
Expect delays and intermittent lane closures on S. Palm Canyon Drive as crews remove beams from the Tahquitz Creek riverbed. Traffic impacts: Thursday, Oct. 1 | 6:30 a.m. to 6:30 p.m.🔶 Watch for trucks entering and exiting the project area with minor traffic delays. Friday, Oct. 2 | 6:30 a.m. to 3 p.m.🔶 Expect short…
Read More🚧 Project Update: Friday, Sept. 24, 2026 🚧
Work continues on the eastern bridge span! Crews are currently building forms for the bridge backwalls—the end walls that help connect the bridge to the approaching roadway—in preparation for an upcoming concrete placement. ☀️ Looking ahead: After the backwalls are poured, crews will begin constructing the bridge approaches on both ends of the eastern span. …
Read More🚧 Construction Alert: Friday, Aug. 28 🚧
An early-morning concrete placement is planned for Friday, Aug. 28, starting at 3 a.m. Crews will be placing concrete for the eastern bridge span deck. Here’s what to expect:🔹 Flaggers will assist concrete trucks entering and exiting the work zone. 🔹 Nearby residents may notice construction lighting and early-morning construction noise. 🔸 Please follow posted project signage, reduce speed…
Read More🚧 Project Update: Week of August 24, 2026 🚧
🔸 Please follow posted project signage, reduce speed through the work zone, and allow extra travel time. ✨ Businesses remain open and accessible—support local all summer! ☀️
Read More🚧 Construction Alert: Week of August 17, 2026 🚧
Crews will begin median construction on S. Palm Canyon Drive north of the bridge. Lane closures will be in place during construction. TRAFFIC IMPACTS: Monday-Friday | Aug. 17 – Aug 21, 2026 | 6 a.m. to 3:30 p.m. • Inside lanes closed on S. Palm Canyon Drive, north of E. Sunny Dunes Road. One lane remains…
Read More✅ Project Milestone!
Crews completed an early-morning concrete placement for the underside of the eastern bridge span! ✨ Businesses in the project area remain open and accessible during construction—thank you for continuing to support local. ☀️ Looking ahead: Crews will begin constructing a median north of E. Sunny Dunes Road on S. Palm Canyon Drive. Crews will also…
Read More🚧 Construction Alert: Monday, August 3, 2026 🚧
Early-morning construction activities planned as crews place concrete on the eastern span interior of the South Palm Canyon Bridge. Here’s what to expect:🔹 Construction activities begin at 3 a.m.🔹 Flaggers will assist concrete trucks entering and exiting the work zone.🔹 Nearby residents may notice construction lighting and early morning construction noise. 🔸 Please follow posted project…
Read More🚧 Project Update: Week of July 20, 2026 🚧
Crews are constructing rebar framing for the underside of the eastern bridge span in preparation for an upcoming concrete pour as Stage 2 construction continues. ✨ Businesses in the project area remain open and accessible throughout construction. This schedule may change due to weather or field conditions. Stay Connected:760-502-0072 | SouthPalmCanyonBridge.com
Read More🚧 Project Update: Week of July 6, 2026 🚧
Progress continues on the eastern span of the new South Palm Canyon Bridge! This week, crews will continue forming the stem and soffit, or the internal portion of the eastern bridge span, of the eastern bridge span in preparation for the next concrete pour. 🔸 Please follow posted signage, reduce speed, and allow extra travel time through…
Read More🚧 Project Update: Week of June 29, 2026 🚧
✅ Crews have completed beam placement for the eastern bridge span. Up next: Crews will continue constructing the bridge forms in preparation for placing rebar and upcoming concrete pours on the eastern bridge span. 🇺🇸 No work is planned for Friday, July 3, in observance of Independence Day. 🔸 Please follow posted signage, reduce speed,…
Read More