🚧 Project Update: Week of July 20, 2026 🚧

Crews are constructing rebar framing for the underside of the eastern bridge span in preparation for an upcoming concrete pour as Stage 2 construction continues. ✨ Businesses in the project area remain open and accessible throughout construction.  This schedule may change due to weather or field conditions. Stay Connected:760-502-0072 | SouthPalmCanyonBridge.com

Read More

🚧 Project Update: Week of July 6, 2026 🚧

Progress continues on the eastern span of the new South Palm Canyon Bridge! This week, crews will continue forming the stem and soffit, or the internal portion of the eastern bridge span, of the eastern bridge span in preparation for the next concrete pour. 🔸 Please follow posted signage, reduce speed, and allow extra travel time through…

Read More

🚧 Project Update: Week of June 29, 2026 🚧

✅ Crews have completed beam placement for the eastern bridge span. Up next: Crews will continue constructing the bridge forms in preparation for placing rebar and upcoming concrete pours on the eastern bridge span. 🇺🇸 No work is planned for Friday, July 3, in observance of Independence Day. 🔸 Please follow posted signage, reduce speed,…

Read More

🚧 Construction Alert: Monday, June 22 🚧

Traffic holds are planned on S. Palm Canyon Drive on Monday, June 22, to allow for the safe delivery of 90-foot-long beams to the project site. Traffic Impacts:Monday, June 22 | 7 a.m. to 6 p.m.🔶 Traffic holds are planned between E. Camino Parocela and Mesquite Avenue.🔶 Flaggers will stop and hold traffic as trucks…

Read More

🚧 Construction Alert: Friday, May 29 🚧

Early morning concrete placement is planned on Friday, May 29, starting at 6 a.m. Traffic impacts:
Friday, May 29 | 6 a.m. to 3:30 p.m.
🔶 Watch for traffic flaggers assisting trucks entering and exiting the job site at both ends of the bridge.
🔶 Expect delays and please use alternate routes. ✨ Businesses remain open and accessible…

Read More

✅ Project Milestone: May 2026

Crews completed the first concrete placement on the eastern bridge span for the retaining wall and footing as Stage 2 construction continues on the South Palm Canyon Bridge Project. 🚧 Thank you to the community for your continued patience and support as work progresses. ✨ Businesses in the project area remain open and accessible during construction. 🚫⬅️ Reminder:…

Read More

Construction Alert: Thursday, May 7, 2026 

Early morning concrete placement is planned on Thursday, May 7 🚧 Traffic impacts:
Thursday, May 7 | 6 a.m. to 3:30 p.m.
 🔶 Watch for traffic flaggers assisting trucks entering and exiting the job site at both ends of the bridge.
 🔶 Expect delays and please use alternate routes. Businesses remain open and accessible during construction. This schedule may…

Read More

Construction Update: Week of May 4, 2026 

🚧 Crews are finishing rebar and formwork for Abutment 1 and the retaining wall as the project prepares for the first concrete placement on the eastern bridge span planned for mid-May. Please check back for updates.  🔸 Please slow down and use caution when traveling through the project area. 🔸 ✨ Businesses in the project area remain open and…

Read More

Project Update: Week of April 27, 2026 

🚧 Construction is underway on the eastern bridge span, with crews working on forms and rebar for retaining walls and footings. Please slow down and use caution when traveling through the project area. ✨ Businesses in the project area remain open and accessible — support local while work continues. Stay Connected:760-502-0072 | SouthPalmCanyonBridge.com

Read More

Project Update: Week of April 20, 2026 

🚧 Progress is building from the ground up 🚧 ✅ Demolition done! Crews are starting work on the eastern bridge span retaining walls and footings that will support the new South Palm Canyon Bridge. Please reduce speed in the project area and plan ahead for possible delays. Businesses remain open and accessible during construction. Stay connected: (760)…

Read More