Construction Alert: Week of February 16, 2026

No construction activity is planned on Monday, Feb. 16, in observance of Presidents Day. The current traffic pattern will remain in place until Tuesday, Feb. 24. Upcoming construction activities are weather permitting. 

Traffic Impacts:

Wednesday, Feb. 18 | Starting at 6 a.m.
• Crews will pave the outside southbound lane on South Palm Canyon Drive starting just north of E. Sunny Dunes Road.
• Traffic control will be in place through the intersection.
• Flaggers will assist construction trucks entering and exiting the project area.
• Motorists may experience brief, minor delays.
• Business access will be maintained.

Thursday, Feb. 19
• Maintenance crews will repair the traffic signal at E. Sunny Dunes Road and S. Palm Canyon Drive.
• The signal will be off, and the intersection will operate as a mandatory four-way stop.
• All routes will remain open and accessible.

Please reduce speed and use caution when traveling through the project area.

Looking ahead:
The Traffic Flip onto the new western bridge span is tentatively scheduled for Tuesday, Feb. 24, in the afternoon. Traffic will shift onto the newly reconstructed western span, and crews will begin demolition of the eastern bridge span.

Businesses remain open and accessible during construction.